Planning

September 2022 through Spring 2023

Groundbreaking

July 2024

Construction Completed

September 2025 (anticipated)

Project Updates

October 25, 2024: Steel structure nearly complete, roofing work underway

The steel structure work is nearly complete, as you can see from the photos (in the photos tab below). Roofing work has also started, as the building begins to take shape.

The project also is nearing completion on an eight-foot retaining wall on the north side. Some necessary stormwater management work occurred on nearby Shooks Run as well.