We have a quick overview of 2C paving and concrete work that's taking place right now in Colorado Springs. For more information about 2C or to see the full paving list, visit coloradosprings.gov/2c.
Week of 9/14/2020
Crews will continue milling and paving operations on the following segments:
STREET |
FROM |
TO |
---|---|---|
FLINTRIDGE DR |
ACADEMY BLVD |
DEAD END |
FLINTRIDGE DR |
VICKERS DR |
MONTEBELLO DR |
JET WING DR |
FOUNTAIN BLVD |
ASTROZON BLVD |
NEVADA AV *Phase 2 |
FILLMORE ST |
*ROCK ISLAND TRAIL BRIDGE |
Crews anticipate beginning milling and paving operations on the following segments:
STREET |
FROM |
TO |
---|---|---|
MESA RD |
FILLMORE ST |
UINTAH ST |
MESA RD |
UINTAH ST W |
WALNUT ST |
CASCADE AV |
DEAD END |
FILLMORE ST |
VERDE DR |
CIRCLE DR |
CHELTON RD |
PIKES PEAK AV |
MURRAY BLVD |
FROST LN |
Crews anticipate completing concrete operations on the following segments:
STREET |
FROM |
TO |
---|---|---|
CASCADE AV |
UINTAH ST |
PLATTE AV |
Crews will continue concrete operations on the following segments:
STREET |
FROM |
TO |
---|---|---|
UNION BLVD |
WOODMEN RD |
ACADEMY BLVD |
PLATTE AV |
UNION BLVD |
WAHSATCH AV |
WESTMEADOW DR |
CHEYENNE MEADOWS DR |
ACADEMY BLVD |
CHEYENNE MOUNTAIN BLVD E |
ROUND-A-BOUT |
SH115 |
Week of 9/7/2020
Crews completed the concrete operations on the following segments:
STREET |
FROM |
TO |
---|---|---|
FLINTRIDGE DR |
ACADEMY BLVD |
DEAD END |