We have a quick overview of 2C paving and concrete work that's taking place right now in Colorado Springs. For more information about 2C or to see the full paving list, visit coloradosprings.gov/2c.
Updates for week of 9/14/2020
This week crews completed the paving operations on the following segments:
STREET |
FROM |
TO |
---|---|---|
FLINTRIDGE DR |
VICKERS DR |
MONTEBELLO DR |
This week crews completed the concrete operations on the following segments:
STREET |
FROM |
TO |
---|---|---|
CASCADE AV |
UINTAH ST |
PLATTE AV |
Plans for the week of 9/21/2020
Timelines are weather and construction dependent.
Next week crews expect to continue milling and paving operations on the following segments:
STREET |
FROM |
TO |
---|---|---|
FLINTRIDGE DR |
ACADEMY BLVD |
DEAD END |
VERDE DR |
CIRCLE DR |
CHELTON RD |
JET WING DR |
FOUNTAIN BLVD |
ASTROZON BLVD |
NEVADA AV *Phase 2 |
FILLMORE ST |
*ROCK ISLAND TRAIL BRIDGE |
MESA RD |
FILLMORE ST |
UINTAH ST |
MESA RD |
UINTAH ST W |
WALNUT ST |
PIKES PEAK AV |
MURRAY BLVD |
FROST LN |
Next week expect to start milling and paving operations on the following segments:
STREET |
FROM |
TO |
---|---|---|
CASCADE AV |
DEAD END |
FILLMORE ST |
WINTERS DR |
CASCADE AV |
NEVADA AV |
TEJON ST |
BOULDER ST |
PLATTE AV |
RIO GRANDE ST W |
CASCADE AV S |
SAHWATCH ST S |
Next week crews expect to continue concrete operations on the following segments:
STREET |
FROM |
TO |
---|---|---|
UNION BLVD |
WOODMEN RD |
ACADEMY BLVD |
PLATTE AV |
UNION BLVD |
WAHSATCH AV |
WESTMEADOW DR |
CHEYENNE MEADOWS DR |
ACADEMY BLVD |
CHEYENNE MOUNTAIN BLVD E |
ROUND-A-BOUT |
SH115 |
Next week crews expect to start concrete operations on the following segments:
STREET |
FROM |
TO |
---|---|---|
SAHWATCH ST S |
CIMARRON ST W |
RIO GRANDE ST W |