Project Overview:

Colorado Springs Utilities and the City of Colorado Springs are partnering to perform construction work on 21st Street. 

Utilities will begin by replacing a water main under 21st Street between Colorado Avenue to Highway 24. After this, the City will install/replace curb, gutter and sidewalk along 21st Street between Colorado Ave and Hwy 24. Maintenance will be performed on the 21st Street Bridge over Fountain Creek to extend its service life.  Finally, 21stStreet will be resurfaced with a new layer of asphalt.

Colorado Springs Utilities Construction activities are expected to begin mid-April and continue through June. Work hours will typically be 7 a.m. to 6 p.m. Monday through Friday and may include night and weekend work.

The City will begin work around June, starting first with the curb, gutter and sidewalk work.  As a result, a new walking trail will be established to provide an alternate connection for the Midland Trail. All construction work is scheduled to be completed by October.

Timeline:

The project will begin mid-April and finish October 2018.

Key Elements:

  • New water main
  • Curb, gutter and sidewalk will be installed/replaced between Colorado Ave. and Hwy 24.
  • The 21st Street Bridge over Fountain Creek will have rip-rap installed around the abutments and piers
  • The existing pavement on the bridge will be removed to install a new waterproof membrane
  • Adding an alternate connection to the Midland Trail

Budget:

Approximate cost is $1,000,000