March 2023
  • Contractor Selected
April 2023
  • Construction Start
September 2023
  • Estimated Project Completion
Construction

The project is part of the overall improvements for Marksheffed Rd. and  consists of widening and restriping of Dublin Blvd. and the restriping of Marksheffel Road to add capacity through the Dublin and Marksheffel intersection. These improvements should reduce intersection queuing and improve safety.

Upload File

The project will add an additional through lane for Marksheffel Road and Dublin Boulevard traffic in all directions through the intersection.  The southbound through lane on Marksheffel will drop approximately 1,000 feet south of the intersection, while the westbound through lane on Dublin will terminate as a forced right turn at Issaquah Drive.