Paving Updates: Mark Dabling, Interpark Drive & Inspiration Drive

Paving

Last week (September 15-21) 2C paving crews completed paving on the following areas.

  • Mark Dabling Blvd (Corporate Drive to Rockrimmon Blvd)
  • Interpark Drive (Private property north to cul-de-sac)
  • Inspiration Drive (Carefree Circle S to Rio Vista Drive)

This week (September 22-28)* 2C crews expect to finish paving on:

  • 21st Street (Colorado Ave W to Cimarron Street)
  • Briargate Parkway (Lexington Dr to Voyager Pkwy)

This week (September 22-28)* 2C crews expect to continue paving work on:

  • Briargate Pkwy (Union Blvd to Lexington Dr)
  • Carefree Circle N (Powers Blvd to Oro Blanco Dr)

This week (September 22-28)* 2C crews expect to start milling and paving on:

  • Lexington Drive (Research Pkwy to Union Blvd)
  • Lexington Drive (Briargate Pkwy to Research Pkwy)

Concrete

Last week (September 15-21) 2C crews finished concrete work on:

  • Union Blvd (Charity Dr to Research Pkwy)
  • Carefree Circle N (Oro Blanco Dr to Academy Blvd N)
  • Astrozon Ct (cul-de-sac to Astrozon Blvd)

This week (September 22-28)* 2C crews expect to finish concrete work on:

  • 21st St S (Colorado Ave W to Cimarron St)
  • Ouray Ave (Cheyenne Rd E to Lynn Ave)
  • Nevada Ave (I-25 Concrete to Eagle Rock Rd)
  • Rockhurst Blvd (Dead end to Whistler Pt)
  • Executive Cr (Janitell Rd E to Janitell Rd E)
  • Executive Cr (cul-de-sac to Janitell Rd E)

This week (September 22-28)* 2C crews expect to continue concrete work on:

  • Austin Bluffs Parkway (E Woodmen Rd - Rangewood Dr)
  • Mirage Dr (Chapel Hills Dr to Union Blvd)
  • Sand Creek Dr (Airport Rd to Airport Rd)
  • Janitell Dr E (Circle Dr S to Janitell Rd)
  • Carefree Circle W (Carefree Circle N to Village Rd S)
  • Union Blvd (Briargate Pkwy to Charity Dr)

This week (September 22-28)* 2C crews espect to start concrete work on:

  • Byron Dr (Pikes Peak Ave to Murray Blvd)

*Project projections are subject to change depending on weather and other conditions.