Main content
In Progress
Spring 2026
  • Anticipated project completion 
    (All work is weather-dependent and subject to change.)
July 2025
  • Construction start 
Spring 2025
  • Design completion
Map of the two intersections at E. Ramona St. and S. Nevada Ave. and St. Elmo Ave. and S. Nevada Ave where the planned traffic signals will go

 

Project Update

The South Nevada Avenue Traffic Signal Improvements Project is resuming construction on Monday, February 2, 2026, as crews return to complete the final stage of work.

What’s Happening On-Site

As work ramps back up, you may notice activity at both Ramona Avenue and St. Elmo Avenue over the next several weeks. Planned tasks include:

  • Installing new traffic signal equipment and connecting electrical systems
  • Setting traffic and pedestrian signal poles
  • Finishing wiring and cabinet work
  • Wrapping up final streetscape and concrete improvements

Traffic & Access

  • Most work will occur using single outside lane closures on South Nevada Avenue.
  • No full closures of Ramona Avenue or St. Elmo Avenue are anticipated.
  • Short-term access restrictions may occur at Ramona Avenue and the nearby gas station driveway when crews are installing signal poles. These closures will be limited to brief, off-peak windows for a few hours as needed.
  • Driveways and side streets will remain accessible throughout construction.
  • Pedestrian routes remain open, with clearly marked and accessible temporary walkways in place.

What’s Completed

Earlier phases of the project, including installation of signal pole foundations and underground conduit work, were completed in August 2025. Pedestrian access remained available in temporary conditions during the holding period.

We appreciate your continued patience as we move into the final stretch of this important safety and mobility project.