In Progress

To see past newsletter updates, click on the "Newsletters" tab on this page.

Department:
City Engineering
Upload File
A cross section of Tejon Street that shows the new parking orientation and right of ways.

 

Workers begin smoothing the concrete expansion of the Tejon St. sidewalk

Construction of the Tejon Street Revitalization Project – to enhance outdoor dining space, sidewalk accessibility, and public safety – is nearly complete. Expanded dining areas,   wider sidewalks and new trees have been installed on Block 1 (Colorado Avenue to Pikes Peak Avenue.) and Block 2 (Pikes Peak Avenue to Kiowa Street). All four corners at Tejon Street and Pikes Peak Avenue – Historic Busy Corner -- have been updated with colorful concrete and curbs that slope gently to street level. 

The project team will take a winter break and return in the spring with final improvements at Busy Corner. 

Relocation of commercial deliveries

At completion, Tejon Street will have a northbound and southbound lane, but the center tune lane will be removed to keep delivery trucks and their drivers out of traffic lanes. Commercial deliveries have moved to alleys and new loading zones on Colorado and Pikes Peak Avenues.