Current Traffic Impacts
Late Feb.–Late May: New traffic configuration between Astrozon Blvd. and El Morro Road
A new traffic configuration is in place on South Academy Boulevard between Astrozon and El Morro Road near Sand Creek. Drivers can expect lane reductions and traffic shifted to the west, with northbound lanes moving to the inside.
The ramps connecting Hancock Expressway to South Academy Boulevard are closed. Drivers will need to use the signalized intersection to make right-hand turns during construction. Plan for minor delays and watch for signs in the area for updates.
The southbound South Academy Boulevard on-ramp to eastbound Milton Proby Parkway is closed to allow crews to perform water and drainage utility upgrades in the area. This closure will be in place approximately until the end of May. Follow posted detour signs. Drivers should slow down in school zones, and drive with care.
Beginning in April, Boychuk Avenue will be reduced to alternating one-lane traffic controlled by temporary signals or flaggers. The bike lane will be closed in this area and bicyclists will need to merge with traffic. This work will last approximately two months and is necessary for prep work for the tie-in of Boychuk Avenue to S. Academy Boulevard. Please be careful when exiting and entering Colorado Car Wash located southwest of Boychuk Avenue. In addition, the Victory Outreach parking lot southeast exit will be closed during this work. View detour map.
Beginning the morning of Monday, April 6, 2026, the McDonald’s driveway at Academy Place Shopping Center (2515 S. Academy Blvd) will be closed from northbound South Academy Boulevard for approximately two weeks (weather dependent). This closure is necessary to excavate a trench approximately 14 feet deep, place watermain pipe, and restore the curb, gutter, and pavement. Businesses at Academy Place Shopping Center remains open and accessible during construction. Customers may access the restaurant via Astrozon Boulevard (right turn only from S. Academy Blvd) or Jet Wing Drive. View detour map.
Safety tip: Slow down, follow signs, watch for workers and equipment, and allow extra time.
About
The South Academy Boulevard Improvements Project will increase safety, mobility, pedestrian access, and drainage along the corridor. The work covers 18 miles of South Academy Blvd. between Bijou St. and Airport Rd.
Between East Fountain Boulevard and Jet Wing Drive (construction to start early 2026)
Work along the corridor focuses on infrastructure improvements, including replacement of aging pavement, curb, and gutter. A new, multi-use path is being constructed on one side of S. Academy Boulevard. The path/sidewalk will improve access for pedestrians and other users. Major drainage improvements are also part of the project and include new manholes, inlets, and drainage pipes. Colorado Springs Utilities is relocating and upgrading water and wastewater lines to support thousands of users in the area.
Pikes Peak Rural Transportation Authority (PPRTA) dollars fund the project.
S. Academy Boulevard Improvement Project Update
Current Status
Segment 1 of the project is complete. Work on the remaining segment beginning in fall 2025 will further improve the overall infrastructure and accessibility of S. Academy Boulevard.
Stay tuned for further updates as we progress through this important community improvement project.
Project Construction Schedule
Construction of the corridor is divided into 2 different segments over the course of 24 months:
- Segment 1 (North) – South Academy Boulevard between Bijou Street and Airport Road
- Started late February 2023
- Completed late 2024
- Segment 2 (South) – South Academy Boulevard between East Fountain Boulevard and Jet Wing Drive
- Public open house September 2025
- Scheduled to start early 2026
Public Information
Construction Updates
- February 22, 2026 / English
- February 22, 2026 / Español
- January 26, 2026 / English
- January 26, 2026 / Español
- January 12, 2026 / English
- January 12, 2026 / Español
Fact Sheets
- September 2, 2025 / English
- September 2, 2025 / Español
- August 5, 2025 / English
- August 5, 2025 / Español
Construction Public Involvement
September 9, 2025 Project Open House
February 16, 2023 Project Open House
Design Public Involvement
Public Meetings
- July 22, 2021 Public Open House
- May 18, 2021 South Academy Blvd - 60% Design - RISE Coalition presentation
- Nov. 17 meeting PowerPoint Presentation
- Frequently Asked Questions – Nov. 2020
Newsletters
Maps
Milton E. Proby Ramp Closure and Detour Route
This closure begins Jan. 21, 2026.
Segment 1: S. Academy Blvd. closure between Hancock Expy. and Drennan Road
Segment 1: S. Academy Blvd. closure between Astrozon Blvd. and Hancock Expy.
Segment 1: S. Academy Blvd. full closure between Astrozon Blvd. and Drennan Road
Segment 1: S. Academy Blvd. & Hancock slip ramp closures
Bus stops affected by S. Academy Blvd. Improvements Project starting week of Jan. 19
Photos
Construction Photos: Segment 2 (South) – South Academy Boulevard between Fountain Boulevard and Jet Wing Drive
Pre-Construction Photos: Segment 2 (South) – South Academy Boulevard between Fountain Boulevard and Jet Wing Drive
Funding
This is a voter-approved, Pikes Peak Rural Transportation Authority (PPRTA) A-listed project.