Published on

We have a quick overview of 2C paving and concrete work that's taking place right now in Colorado Springs. For more information about 2C or to see the full paving list, visit coloradosprings.gov/2c.

Week of 9/14/2020

Crews will continue milling and paving operations on the following segments:

Milling

 STREET

FROM

TO

FLINTRIDGE DR

ACADEMY BLVD

DEAD END

FLINTRIDGE DR

VICKERS DR

MONTEBELLO DR

JET WING DR

FOUNTAIN BLVD

ASTROZON BLVD

NEVADA AV *Phase 2

FILLMORE ST

*ROCK ISLAND TRAIL BRIDGE

 

Crews anticipate beginning milling and paving operations on the following segments:

Milling and paving

 STREET

FROM

TO

MESA RD

FILLMORE ST

UINTAH ST

MESA RD

UINTAH ST W

WALNUT ST

CASCADE AV

DEAD END

FILLMORE ST

VERDE DR

CIRCLE DR

CHELTON RD

PIKES PEAK AV

MURRAY BLVD

FROST LN

 

Crews anticipate completing concrete operations on the following segments:

Concrete operations

 STREET

FROM

TO

CASCADE AV

UINTAH ST

PLATTE AV

 

Crews will continue concrete operations on the following segments:

Concrete operations

 STREET

FROM

TO

UNION BLVD

WOODMEN RD

ACADEMY BLVD

PLATTE AV

UNION BLVD

WAHSATCH AV

WESTMEADOW DR

CHEYENNE MEADOWS DR

ACADEMY BLVD

CHEYENNE MOUNTAIN BLVD E

ROUND-A-BOUT

SH115

 

Week of 9/7/2020

Crews completed the concrete operations on the following segments:

Concrete operations

 STREET

FROM

TO

FLINTRIDGE DR

ACADEMY BLVD

DEAD END

 